Dear SEES Users,
This is a reminder that the proposal and beamtime request deadline
for the APS 2024-3 run is this Friday, June 28. If you submitted a proposal for the previous 2024-2 cycle you must still submit a beamtime request for 2024-3 if you want beamtime.
13-BM: The shielding verification for the GSECARS bending magnet stations is scheduled for July 10. We will then have about a month of technical commissioning before
the APS shuts down from August 12 through September 16. We expect to run user experiments for most of the 2024-3 run.
13-ID: The shielding verification for the GSECARS undulator stations is scheduled for the beginning of August. We will be doing technical commissioning when the
APS comes back on September 16. We hope to run some user experiments near the end of the 2024-3 run.
Best regards,
Mark Rivers
Chief Technology Officer, SEES